Palawan Electric Cooperative

TOTAL BLACKOUT UPDATE

TOTAL BLACKOUT UPDATE
November 21, 2025 | as of 9:30 AM
Information from National Transmission Corporation (TransCo) – Palawan
System Operation
Description of Outages:
Total System Blackout (TSB) at Palawan Grid
Date: November 21, 2025
Time of Incident: 5:30 AM
Affected Area: Brooke’s Point to Taytay, Palawan
Weather: Light Rain at Puerto Princesa
Initial assessment: The Total System Blackout (TSB) was caused by cascaded
tripping of power plants due to the activation of Delta P CB13 transformer
differential relay.
Remarks: Ongoing restoration