Palawan Electric Cooperative

ELECTRICITY DEMAND

Puerto Princesa City is the main contributor in PALECO’s energy sales and demand having a total of 61.60%. The table below shows the energy sales and demand of each distribution system. Narra distribution system starts from Barangay Inagawan in the southern part of Puerto Princesa City. Brooke’s Point distribution system covers the Municipalities of Brooke’s Point, Bataraza and part of Sofronio Española. Further, Cuyo distribution system supplies the whole island comprises of Cuyo and Magsaysay.


PALECO’s total system loss for all the distribution systems as of December 2021 is 9.48% which is lesser than the allowable 13% set by the Energy Regulatory Commission (ERC) for all electric cooperatives.

DAILY SUPPLY & DEMAND OUTLOOK

January 31, 2024
(MW)
Morning
0001H-1200H
Afternoon
1201H-1800H
Evening
1801H-2400H
Power Supply
59.52
62.13
62.62
Maximum Load Demand
56.12
58.73
59.22
Power Supply Reserve/(Deficit)
3.40
3.40
3.40

No Data Found

The forecasted EC’s maximum load demand nominated a day ahead to the EC’s power supply provider/s over a 24-hour period.

 

POWER SUPPLY:

The power to be supplied by the EC’s power supply provider/s based on the EC’s maximum load demand nominated a day ahead over a 24-hour period

 

MAXIMUM LOAD DEMAND:

The forecasted EC’s maximum load demand over a 24-hour period.

 

POWER SUPPLY RESERVE/(DEFICIT):

The difference the power supply and EC’s maximum load demand over a 24-hour period