Partial Power Interruption Final Update 5/27/25 3:18 PM

Partial Power Interruption Final Update 5/27/25 3:18 PM
Petsa: May 27, 2025
Oras Na Nawalan: 2:49 PM
Apektadong Lugar:
Under SAN JOSE CIRCUIT: Brgy. San Jose, Brgy. San Manuel, Brgy. Tagburos,
Brgy. Sta. Lourdes hanggang Sitio Magarawak at iilang bahagi ng Brgy.
Sicsican.
Under FACTOR RECLOSER: Brgy. San Manuel, Brgy. San Pedro, Brgy. San Miguel,
Naval Road, 570th Composite Tactical Wing Compound at Naval Compound
Oras Na Naibalik:
3:07 PM – San Jose Initial Manually Close
3:10 PM – San Manuel Recloser Manually Close
Detalye: Nag-trip ang isang unit ng Delta P-Unit 3 (7.2 MW) na nagresulta
sa pag-activate ang Automatic Load Dropping (ALD) ng San Jose Circuit at
Factor Recloser. Ongoing na din ang restoration ng power sa Factor at
Mendoza Recloser.