Palawan Electric Cooperative

Partial Power Interruption Final Update

Partial Power Interruption Final Update
Petsa: February 7, 2025
Oras Na Nawalan: 9:21 PM
Apektadong Lugar: Under Lucbuan feeder 2: Brgy. Lucbuan, Brgy. Babuyan,
Brgy. San Rafael, Brgy. Concepcion, Brgy. Binduyan hanggang Brgy. Langogan
Oras Na Naibalik: 9:43 PM
Detalye: Emergency load shedding due to preventive maintenance of DMCI
Thermal (15MW) and Corrective Maintenance Delta P unit DG 1 & 2 ( 14.4 MW).”