Partial Power Interruption Final Update 7/6/23 3:10 PM
Petsa: July 6, 2023
Oras Na Nawalan: 2:32 PM
Apektadong Lugar: Under IWAHIG CIRCUIT: Brgy. Sta. Monica, Brgy. Tiniguiban
kasama ang San Jose initial
Oras Na Naibalik: 2:45 PM
Detalye: Nagkaroon ng ALD (Automatic Load Dropping) Dahil nagtrip ang DMCI
Narra Thermal power plant. Nagtrip din ang 69kv transmission line ng NPC
simula DMCI Narra thermal papuntang NPC Brooke’s point.
Petsa: July 6, 2023
Oras Na Nawalan: 2:32 PM
Apektadong Lugar: Under IWAHIG CIRCUIT: Brgy. Sta. Monica, Brgy. Tiniguiban
kasama ang San Jose initial
Oras Na Naibalik: 2:45 PM
Detalye: Nagkaroon ng ALD (Automatic Load Dropping) Dahil nagtrip ang DMCI
Narra Thermal power plant. Nagtrip din ang 69kv transmission line ng NPC
simula DMCI Narra thermal papuntang NPC Brooke’s point.